CETF & No CapX Motion Denied!

Filed under:ITC MN & IA 345 kV — posted by admin on April 1, 2014 @ 11:10 am

Here’s the Order, hot off the press:

Order Denying Motions

Onward…

Testimony in ITC MN/IA docket filed

Filed under:ITC MN & IA 345 kV — posted by admin on @ 9:16 am

pilesofiles

Piles and piles of papers…

Applicant Testimony

Ashbacker Direct

Berry Direct

Coeur Direct

Grover Direct

Middleton Direct – Schedules 1-14

Schatzki Direct

MISO Testimony

Chatterjee Direct

Commerce Testimony

Heinen Direct

Heinen Direct_Attachments

Johnson Direct– THIS IS A MUST READ!!!

Rakow Direct

MCEA et al. Testimony

Goggins Direct

CETF – No CapX2020

(no testimony, no funding = no witnesses)

Reply to MCEA, et al. Response to Motion to Compel

Filed under:ITC MN & IA 345 kV — posted by admin on @ 9:02 am

mud-wrestling

Because the ITC Midwest MN/IA 345 kV transmission project (part of MISO MVP 3) is connected to the Badger Coulee (part of MISO’s MVP 5) project from La Crosse to Madison, I’ll be posting updates on the ITC docket here.  CETF and No CapX2020 have intervened, and are now requesting additional leeway for participation

Just filed, the Affidavit in support of our Reply, here’s the series of filings, focused on getting in the record the deals that have gotten us where we are today…  In chronological order:

CETF and No CapX2020 Motion to Compel

ITC Response to Motion to Compel

MCEA et al., Response to Motion to Compel

MCEA et al, Affidavit_20143-97498-03

CETF and NoCapX Reply to Response to Motion

Affidavit of Overland – Reply to Response to Motion

The next Prehearing Conference is on Thursday, April 3 at 1:30 p.m.