Fargo DEIS Comments due TODAY
Here’s the DEIS for the CapX 2020 Fargo-St. Cloud transmission line:
Here’s Notice of it and official info:
Send Comments to David Birkholz, the MOES Project Manager:
david.birkholz@state.mn.us
or mail to:
David Birkholz
Fargo-St. Cloud EFP Project Manager
MN Dept of Commerce
85 – 7th Place East, Suite 500
St. Paul, MN 55101
2 comments »
Copy link for RSS feed for comments on this post or for TrackBack URI
Hello David,
With an existing uninterupted corridor in I-94 from St. Cloud to Fargo, I strongly urge a long look at the process in which the CAPX2020 could utilize this path. I would like to see a cost benefit analysis comparing underground lines using the corridor vs the conventional tower lines over a timeline of 5, 10, 20, & 30 years.
Thank you,
Eric Fowler
Comment by Eric Fowler — October 18, 2010 @ 7:07 pm
If lines must cross our property, please add NE of existing lines.
Comment by Martin Hackenmueller — October 19, 2010 @ 6:13 pm