2nd Petition for Intervention in Xcel Rate Case

Filed under:Cost Recovery,PUC Docket,Rate Case - Transmission — posted by admin on January 24, 2016 @ 11:15 pm

gavel

Apparently Judge Oxley did not like the Overland and No CapX 2020 Petition for Intervention in the rate case, late Friday the Order came out.  It was denied, without prejudice.  And yet interventions for Commercial Group, Suburban Rate Authority, and City of Minneapolis were granted…

20161-117574-01_Order Denying Intervention

… sigh… OK… fine…

Just filed at 12:01 a.m. Monday, January 25, 2016:

Overland-NoCapX_Intervention2_FINAL

These transmission issues being raised about CapX 2020 and the MISO MVP 17 Project Portfolio are so important that I’m going to be persistent.

Here’s the schedule, from the First Prehearing Order:

schedule