Monday August 9 – Scheduling Conference for Hampton-Alma routing

NO Grid North Partners - transmission f/k/a CapX 2020 Posted on July 26, 2010 by adminJuly 26, 2010

Here we go again… Administrative Law Judge Kathleen Sheehy has file notice of a Scheduling Conference for the CapX 2020 Hampton-Alma/LaX transmission line routing permit docket — it’s the Monday after next. Monday, August 9 @ 1:30 p.m. Scheduling Conference … Continue reading →

Posted in Hampton-Alma-LaCrosse | Tagged CapX 2020, CapX 2020 transmission, CapX2020, Hampton-Alma transmission line, Hampton-LaCrosse transmission line, NoCapX 2020, powerline, transmission, transmission line | Leave a reply

MOES ignores Watershed organizations

NO Grid North Partners - transmission f/k/a CapX 2020 Posted on July 24, 2010 by adminJuly 24, 2010

The “Citizen Advisory Task Force Reports” for the CapX 2020 Hampton-Alma/LaX transmission line are out: Final Hampton-Northern Hills 345kV Transmission Line ATF Report Final North Rochester-Mississippi River 345kV Transmission Line ATF Report Early on in the Hampton-Alma/LaX Citizen Advisory Task … Continue reading →

Posted in Hampton-Alma-LaCrosse | Tagged Belle Creek Watershed District, Cannon River Watershed Partnership, Zumbro Watershed Partnership | Leave a reply

Death threats in the mail?!?!?

NO Grid North Partners - transmission f/k/a CapX 2020 Posted on June 2, 2010 by adminJune 2, 2010

Death threats to an Advisory Task Force member?  Well, that’s different! I’ve just come back from the Cannon Falls Citizen Advisory Task Force for the CapX 2020 Hampton-Alma/LaCrosse transmission line route.  Got there just a tad-bit late, and learned I … Continue reading →

Posted in Hampton-Alma-LaCrosse | Tagged CapX 2020, Holden Township, Karen Doll, NoCapX, NoCapX 2020, Pine Island, Pine Island EDA, Sogn Valley, United Citizen Action Network | 2 Replies

Data Practices Act Request on CATFs

NO Grid North Partners - transmission f/k/a CapX 2020 Posted on May 30, 2010 by adminMay 30, 2010

You all know how disgusted I’ve been watching Citizen Advisory Task Forces devolve over the last decade, from a group that could meaningfully participate in a routing/siting proceeding to a neutered exercise in choreographed futility.  In these proceedings, we’ve had … Continue reading →

Posted in Hampton-Alma-LaCrosse, Laws & Rules | Tagged CapX 2020, Citizen Advisory Task Force, Data Practices Request, NoCapX 2020 | Leave a reply

CapX 2020 Responds to NoCapX Motion to Suspend

NO Grid North Partners - transmission f/k/a CapX 2020 Posted on May 24, 2010 by adminMay 24, 2010

Here’s their Response: CapX Response to NoCapX & U-CAN Motion to Suspend Where they actually say: Intervenors’ assertion that uncertainty about Midwest Independent Transmission System Operator, Inc. (“MISO”) cost allocation methodologies somehow warrants delay of the Brookings Project routing proceeding … Continue reading →

Posted in Brookings Routing Docket, Hampton-Alma-LaCrosse | Tagged Brookings to Hampton, CapX 2020, cost allocation, Hampton Substation, Hampton to Alma, powerline, transmission line, Xcel Energy | Leave a reply

Mn DOT’s & MRPC Comments on Hampton-Alma/LaCrosse

NO Grid North Partners - transmission f/k/a CapX 2020 Posted on May 24, 2010 by adminMay 24, 2010

The Minnesota DOT’s comments on the scope of the EIS for the CapX 2020 transmission line from Hampton to Alma/LaCrosse are posted. Mn DOT Scoping Comments May 20, 2010 And the Mississippi River Parkway Commission comments are posted too: Mississippi … Continue reading →

Posted in Hampton-Alma-LaCrosse | Tagged Add new tag, CapX 2020, CapX2020, DOT, Hampton-Alma-LaCrosse, Mississippi River Parkway Commission, Mn DOT, NoCapX 2020, powerline, transmission line | Leave a reply

CapX 2020 in the news!

NO Grid North Partners - transmission f/k/a CapX 2020 Posted on May 23, 2010 by adminMay 23, 2010

CapX 2020 transmission is in the news again: Power substation won’t eat up 20 acres of Holmen TIF district By ADAM BISSEN Special to the Tribune | Posted: Saturday, May 22, 2010 12:00 am HOLMEN – Holmen won’t lose 20 … Continue reading →

Posted in Hampton-Alma-LaCrosse, News coverage | Tagged CapX 2020, CapX 2020 transmission, Hampton-Alma-LaCrosse, Hampton-LaCrosse transmission line, transmission line | Leave a reply

Motion to Suspend Proceedings!

NO Grid North Partners - transmission f/k/a CapX 2020 Posted on May 20, 2010 by adminMay 20, 2010

We’re tryin’ — the fun never sets… Today NoCapX 2020 and United Citizens Action Network filed a Motion in two routing dockets — the Brookings-Hampton (PUC Docket 08-1474) and Hampton-Alma (PUC Docket 09-1448) — to suspend the proceedings based on … Continue reading →

Posted in Appeal, Brookings Routing Docket, Hampton-Alma-LaCrosse | Tagged Brookings-Hampton, CapX 2020, Hampton-Alma-LaCrosse, Hampton-LaCrosse, NoCapX 2020, powerline, transmission, transmission line | 1 Reply

Scoping Comments due May 20!!!

NO Grid North Partners - transmission f/k/a CapX 2020 Posted on May 18, 2010 by adminMay 18, 2010

RU

Continue reading →
Posted in Hampton-Alma-LaCrosse | Tagged CapX 2020, CapX 2020 transmission line, NoCapX 2020, powerline, transmission line | Leave a reply

CapX 2020 in the news

NO Grid North Partners - transmission f/k/a CapX 2020 Posted on May 14, 2010 by adminMay 14, 2010

Recent coverage of the CapX 2020 transmission line EIS Scoping Meetings for the Hampton-Alma route (f/k/a Hampton-LaCrosse): CapX concerns at 52/19; comment until May 20 by Ken Haggerty Minnesota Office of Energy Security (MOES) public meetings on the CapX2020 high … Continue reading →

Posted in Hampton-Alma-LaCrosse | Tagged CapX 2020, Minnesota Office of Energy Security, MOES, powerline, transmission, transmission line, Xcel Energy | Leave a reply

Post navigation

← Older posts
Newer posts →
pages
  • About
  • Maps – CapX 2020
search
categories
  • * CURRENT PROJECTS
    • Big Stone-Alex-Big Oaks
    • Brookings-Lyon Co & Helena-Hampton
    • HVDC Modernization Project
    • Lyon Co. – Sherco – MN Energy CON
    • Northland Reliability Project
    • Prairie Island Dry Cask Storage
    • Wilmarth-North Roch-Tremval WI
    • Xcel Energy IRP
  • * OLDER TRANSMISSION
    • Appeal
    • BadgerCoulee – Wisconsin
    • Bemidji-Grand Rapids
    • Brookings Routing Docket
    • Cardinal-Hickory Creek
      • RUS EIS
    • Fargo-St Cloud
    • Hampton-Alma-LaCrosse
    • ITC MN & IA 345 kV
    • Q-1 Upgrade
    • South Dakota
    • St.Cloud-Monticello
  • Buy the Farm
  • Cost Recovery
  • FERC
  • Laws & Rules
  • News coverage
  • Nuts & Bolts
  • PUC Docket
    • Information Requests
  • Rate Case – Transmission
  • Reports – Documents
  • Uncategorized
  • Upcoming Events
  • Wisconsin
archives
  • 2024
  • 2023
  • 2022
  • 2021
  • 2019
  • 2018
  • 2017
  • 2016
  • 2015
  • 2014
  • 2013
  • 2012
  • 2011
  • 2010
  • 2009
  • 2008
  • 2007
©2025 - NO Grid North Partners - transmission f/k/a CapX 2020
↑