Do we really need to do this AGAIN?!?!?!

Filed under:News coverage,Reports - Documents — posted by admin on March 15, 2021 @ 10:38 pm

CapX 2020 is now “Grid North Partners.” Do we really need to go through this AGAIN? Contact them at info@gridnorthpartners.com to be added to their mailing list.

WHAT ABOUT DISTRIBUTED GENERATION DO YOU NOT UNDERSTAND?

2020 CapX2050 Vision Report:  CapX2050_TransmissionVisionReport_FINAL.pdf

How much more transmission can you possibly need? Oh, right, it’s not based on “need” anymore, and you’ve got your new “business plan” and make a lot more on capital expenditure ROI than selling electricity.

Need? Demand is down, down, down, not back to 2006 levels.

And those billions in CapX 2020 expenditures sure worked for you, rates are up, up, up!

May I live as long as Myer Shark and continue to be a pain in your corporate patoot! Have portable office, will travel… and I do so miss being on the road. Here we go!

This is just so nauseating though… as if there isn’t enough to do…

Quacks like a conflict…

Filed under:Cardinal-Hickory,News coverage,Nuts & Bolts,RUS EIS — posted by admin on December 12, 2018 @ 11:20 am

Looks like a conflict, quacks like a conflict, but maybe it’s just a duck?  A duck following the money?

ELPC in the news:

“It doesn’t fully do what’s required … which is to rigorously explore and objectively evaluate all reasonable alternatives,” said Howard Learner, executive director of the Environmental Law and Policy Center. “It assumes that a huge and expensive interstate transmission line must be built and doesn’t fully and fairly evaluate all reasonable alternatives.”

Here’s the full article:

Power line opponents pan draft review of Dubuque-Middleton transmission project

Here are links to the USDA RUS EIS:

RUS EIS for Cardinal-Hickory Creek released!

Let’s think about this… it’s hard to wrap my head around… Howard Learner opposing a transmission project?  After all the dough Environmental Law and Policy Center got to promote transmission?  Remember the transmission love fest held by ELPC where transmission opponents were not allowed to attend??

Here’s the press release from the ELPC site:

New Environmental Study of Proposed Cardinal-Hickory Creek Transmission Line Improperly Rejects Alternatives

FOR IMMEDIATE RELEASE:

Chuck Tenneson, charles@driftlessconservancy.org, 608-930-3252

Sarah Eddy, seddy@elpc.org, 312-795-3710

DODGEVILLE, Wis., Dec. 10, 2018 – The draft environmental impact statement (EIS) released recently by the U.S. Department of Agriculture’s Rural Utilities Service (RUS) for the proposed Cardinal-Hickory Creek transmission line includes only a cursory review of non-transmission alternatives to the high-voltage line such as greater energy efficiency, local renewables, and energy storage, despite requirements in federal law that alternatives be considered thoroughly. The draft EIS admits that non-transmission alternatives, along with lower-voltage and underground alternatives, were “not carried forward for detailed analysis.”

The proposed Cardinal-Hickory Creek transmission line in southwest Wisconsin would cut a swath through the state’s scenic and ecologically unique Driftless Area. The cost of the project would be borne by electric ratepayers in Wisconsin and other states and energy experts have concluded that the new transmission line is not needed due to flattened demand for electricity in Wisconsin and recent advances in energy technology.

The costs and environmental damage that would be created by the transmission line has sparked opposition and legal challenges from local grassroots citizens and conservation groups. Wisconsin’s Dane and Iowa Counties voted to oppose the transmission line and have intervened in the Public Service Commission proceedings to fight the project.

“We wouldn’t think of putting a power line across the Grand Canyon, so why would we think of putting one through one of the most beautiful and unique landscapes in the Upper Midwest?” Said Dave Clutter, executive director of the Driftless Area Land Conservancy. “We have a national treasure in the Driftless Area, and we should treat it like one.”

“RUS is required by federal law to ‘rigorously explore and objectively evaluate all reasonable alternatives’ to proposed transmission lines like the Cardinal-Hickory Creek project,” said Howard Learner, one of the Environmental Law and Policy Center attorneys representing DALC. “RUS cannot simply look at different environmentally harmful routes for this huge transmission line and call it a day.”

“Iowa County residents have come together to adamantly oppose this unneeded high-voltage power line, which would irreversibly damage the landscape, ecology, and recreation economy we depend on,” said Betsy D’Angelo, a member of the Driftless Defenders’ leadership team. “There are alternatives that can improve our electric system without damaging the Driftless Area’s most important natural areas.”

“The draft environmental impact statement for the Cardinal-Hickory Creek project ignores the reality of new technology that has improved energy efficiency and decreased the demand for electricity,” said David Meylor, chairman of the Western Dane Preservation Campaign, the Mount Horeb area citizens group formed to oppose the line. “Recent analyses of electric demand demonstrate that the expensive, invasive Cardinal-Hickory Creek transmission line project simply isn’t needed.”

“The proposed Cardinal-Hickory Creek Transmission line will have a significant negative impact on fish and wildlife habitat and the management of public lands in Southwestern Wisconsin and in light of other energy alternatives should not be constructed,” stated George Meyer, Executive Director of the Wisconsin Wildlife Federation.

The proposed Cardinal-Hickory Creek transmission line would install towers of up to 175-feet along a 100-mile route that would affect sensitive natural areas and disrupt economic activity. The project could cost ratepayers more than $1 billion during the life of the project, including a profit margin for the transmission line’s utility owners that is guaranteed by Wisconsin law.

Legal counsel for the Driftless Area Land Conservancy will be reviewing the RUS’s draft EIS in greater detail and will submit comprehensive public comments to the agency. Members of the public are strongly encouraged to submit comments before the deadline of Feb. 5, 2019.

###

Issued by:

Driftless Area Land Conservancy

Driftless Defenders

Environmental Law and Policy Center

Western Dane County Preservation Campaign

Wisconsin Wildlife Federation

ITC’s MVP 3 Line is energized

Filed under:ITC MN & IA 345 kV,News coverage — posted by admin on November 2, 2018 @ 10:32 am

The MPV3 line they’re referring to below is the red line above. The MVP projects were, at the time, estimated to cost $5.24 BILLION, to be divided between states.  This MVP project was one where NoCapX was a limited intervenor, and one where the Dept. of Commerce inexplicably did a 180 in its testimony, from saying “no need” to claiming need.  Yeah, right… And then there’s the matter of testimony under oath — the ALJ refused. WHAT?!?!  No excuse for that, it’s a part of the ALJ’s job.  Minn. R. 1400.5500(F).  Here’s a contemporaneous rehash of that mess:

ITC Midwest transmission hearing OVER!!??!!

And today, an announcement that Line 3 has been energized.  It’s in the Albert Lea Tribune, note the byline “By Submitted.”  That means that ITC sent them a press release, right?  This isn’t news, it’s an unpaid advertisement.

ITC Midwest energizes new electric transmission line in southern Minnesota

MISO bars access to planning meetings

From the public meeting materials, here’s what they’re looking at, above.  These are significant additions to the transmission grid in Minnesota and Wisconsin.  Look at the number of double circuits they want to add, and look at the new transmission planned for Minnesota and WIsconsin.  And note how, as with CapX 2020, it’s starting in the coal fields of the Dakotas.

MISO’s Economic Planning Users Group is planning a “Regional Transmission Overlay Study” and they’re having another meeting tomorrow, May 25, 2017 down in Metatairie, Louisiana.

Here’s the call in info:

WebEx Information
Event Number: 966 575 350
WebEx Password: Ts824634

Participant Dial-In Number: 1-800-689-9374
Participant Code: 823713

Meeting Materials from the MISO site:

Here’s the problem — they close the meeting, and people like me aren’t allowed to attend.  First I was told, back in January when I tried to register:

Thank you for registering for the Economic Planning Users Group (EPUG) on Jan 31.  The afternoon portion of this meeting will be held in CLOSED session and reserved from MISO Members or Market Participants only.  Please feel free to attend the morning session from 11:00 am to 12:45 pm ET / 10:00 am to 11:45 CT.

I filled out their “CEII – Non-Disclosure Agreement” form and fired it off.  But noooooo…

So next I went to the PUC’s Quarterly MISO update, where I was assured that we could make arrangements so that I could attend.  I resent the “CEII – Non-Disclosure Agreement” and went back and forth and it came to this (click for larger version).  Note this “explanation” of options to be able to attend:

The reason that you were not permitted to attend the closed session is because the meeting involved discussion of Critical Energy Infrastructure Information (CEII) and CEII access requests by Non-Member Individuals requires FERC clearance.  Another access option is to be included on Appendix A of a MISO member or Market Participant.

So that says there are two ways to gain access, 1) get “FERC clearance” or 2) “Another access option is to be included on Appendix A of a MISO member or Market Participant.“  One or the other. Emphasis added.  Here’s the email (click for larger version) laying out those two options:

Oh, I says to myself, off to FERC.  I sent in the requisite paperwork to FERC, and got “FERC clearance” and they shipped me the CEII information, including but not limited to the map.  I let MISO know I’d obtained “FERC clearance,” and here’s the response (click for larger version):

ARRRRGH, they have my CEII NDA on file, have had it since January 23, 2017.  I resent it to the writer of these emails on March 4, 2017, and I sent it again today, and objected to yet another change in their “rules” (click for larger version):

So the plot thickens — from MISO (click or larger version):

And from moi (click for larger version):

LTE in Dodgeville Chronicle

Filed under:Cardinal-Hickory,ITC MN & IA 345 kV,News coverage,RUS EIS,Wisconsin — posted by admin on December 8, 2016 @ 8:12 am

mvp345

See the lower 1/2 of MISO’s MVP project 5, running from near Dubuque, IA to the northeast to the “Cardinal” substation near Madison?  That’s the Cardinal – Hickory Creek transmission line.

The Dodgeville Chronicle ran my Letter to the Editor, just in time for the meeting last night, held by Rural Utilities Service, about the Cardinal – Hickory Creek transmission project:

From 4-7 p.m. on Wednesday, December 7th, the Rural Utilities Service (RUS) is hosting a scoping meeting at the Deer Valley Lodge in Barneveld. RUS will again collect scoping comments for its Environmental Impact Study as it decides on a loan to Dairyland Power Cooperative for a share of project costs. RUS held scoping meetings October 31-November 3, 2016 – why more scoping meetings now?

The Cardinal-Hickory Creek transmission project stretches from a substation near Peosta, across the Mississippi River and Wisconsin, near Dodgeville, to a substation near Madison. Last April, as reported in this paper, American Transmission Company’s Jon Callaway reported that the project schedule had been pushed out to 2018 or beyond. The reasons weren’t clear, and should be specified and made part of the RUS record.

Cardinal-Hickory Creek and the under-construction Badger-Coulee transmission lines are MISO’s (Midcontinent Independent System Operator, Inc.) MVP project “five” revealed five years ago in MISO’s MTEEP 11 report. That was 2011, and it was “postponed” in 2016. Why the delay? MISO’s 12.38% rate of return for construction has been successfully challenged in federal court. There’s a glut of electricity where even marketing electricity cross country is not alleviating the industry’s overproduction. MISO’s MVP economic modeling no longer hold under current scenarios. And maybe the delay is that and more!

Now’s the time to tell RUS to consider the economics, need and causes of delay in its financing decision. If delay is right for the project developers, RUS should also delay, and put financing on hold.

Carol A. Overland, Esq.
Red Wing, MN

RUS’ Cardinal-Hickory Creek meetings

Filed under:Cardinal-Hickory,Laws & Rules,News coverage,Nuts & Bolts,RUS EIS,Upcoming Events,Wisconsin — posted by admin on December 7, 2016 @ 7:16 am

20161206_1655071

Slow evening at Rural Utilities Service’s (RUS) scoping meeting for the Environmental Impact Statement for the Cardinal – Hickory Creek transmission project.  RUS is involved because Dairyland Power Cooperative (DPC) plans to hold a 9% undivided interest in the project, and are looking to RUS to provide the funding.  RUS held two more meetings, following on prior meetings October 31 and November 1 & 2, because their notice for those meetings went out a day late, so another Notice went out:

Notice of Intent To Hold Public Meetings and Prepare Environmental Impact Statement (October 18, 2016

Second Notice_2016-27988-2

Where’s my prior post on these meetings?  It’s gone! Here’s the dates and locations (click for larger version) — the last one is tomorrow in Barneveld, Wisconsin:

noice12-6-7-2016

So to make quick work of it, this is cut and pasted from the RUS Cardinal Hickory Creek page:

I had a quick chat with Dennis Rankin who’s in charge of the environmental review on this and the Dairyland Q-1 South projects, and had a few quick things to register, particularly that ATC has announced that the project is delayed:

ATC postpones Cardinal-Hickory Creek project – The Dodgeville Chronicle -Dodgeville, WI

I had this article and a few comments to add tonight, and will file more detailed comments before the deadline — now January 6, 2017.

Overland-Legalectric Preliminary Comments Cardinal-Hickory Creek(don’t worry, I’ll get this looking pretty by the deadline!)

20161206_1654551

On the way in, there was new transmission marching across the countryside, so ugly:

xmsn-mvp

And look how close to this house in New Vienna, right up near the garage, and not far from the house either — this line cut right through the middle of town:

20161206_1550331

20161206_1551041

newvienna1

But all in all, it was a beautiful day for a drive today!

20161206_1543442

CapX 2020 — It’s over, it’s done, all but the cost recovery

20140512_161838_resized

CapX 2020 at Highway 61 south of Wabasha

Monday, they had their CapX 2020 Love Fest at the Hampton substation, and I didn’t even get an engraved invitation.  It’s a depressing point in time — 12 years on this project — and they got all they wanted, in some places not where they wanted it, but it’s up, and so many people affected.  Having it routed somewhere, anywhere, is what they cared about, and supposedly it’s now “in-service,” though I wonder.  Is it time to have a big bonfire of all the boxes of files?

This was about the Minnesota portions, but South Dakota, North Dakota, and Wisconsin is permitted as well, the superhighway from the coal fields of the Dakotas to Madison and beyond.  Yeah, I could have camped out and crashed the party, but I had another commitment, so couldn’t spend the day hanging out waiting, watching.  Maybe I should have…

capx_hrl_energized_20160926_113428-medLeft-to-right: Mark Kotschevar, Rochester Public Utilities; Dave Geschwind, Southern MN Municipal Power Agency; Teresa Mogensen, Xcel Energy; Chris Kunkle, Wind on the Wires; Ben Porath, Dairyland Power Cooperative; Priti Patel, MISO; Tim Noeldner, WPPI Energy. From CapX Press Release

How much was “Wind on the Wires” (f/k/a Izaak Walton League) (and many other orgs?) paid for their promotion of transmission?

In the press:

STrib (is it really $2.1 billion?  Any recent reports?):

Last Minnesota leg of $2.1 billion electricity mega-project done

From WKBT (video here):

CapX2020 transmission line completed

And Wisconsin Public Radio:

Collaborative Utility Project Connects Electric Transmission From South Dakota To Wisconsin

Rochester Post-Bulletin:

Drone patrols the power line

It’s up and running — get out those gauss meters and check it out.

20140512_161913_1_resized

CapX 2020 at Hwy. 61 looking towards the Mississippi

September 26 — Mark Your Calendars!!

Filed under:Hampton-Alma-LaCrosse,News coverage,Upcoming Events — posted by admin on September 16, 2016 @ 11:50 am

hamptonsubstation

CapX 2020/Xcel Energy is holding a PR shindig, firing up the Hampton – La Crosse leg of its transmission build-out.  Their scheme, their scam, is nothing to celebrate.  But yes, there’s an event coming up… and it should be appropriately observed… where did I put that “No CapX 2020” banner?

September 26, 2016

Time?  They’re not telling…

Hampton Substation

Highway 52 and 215th Street (N. of Hwy. 50)

This project has been 12 years of my life… first got wind of it in 2004 at a MAPP NM-SPG meeting, though really, it was apparent with the release of the WIREs-WRAO Report from 1998.  That was 18 years ago.  Transmission is not rocket science!  As we say, “It’s all connected!”  Oh, but wait… for the purposes of the Minnesota Certificate of Need proceeding, we couldn’t connected all the dots, and the CapX folks insisted that it only went to La Crosse!!!  Oh, please…

terminatelax

Anyway, the planed shindig was reported in the Rochester Post Bulletin:

Nice try, Tim. My identity is a more closely guarded secret than Colonel Sanders’ recipe. But if you’d like to send me a piece of cake, I can’t stop you.

Have messages in to both Tim Carlsbad and Grant Stevenson, but the timing is top secret, no invitation is forthcoming, so I guess I’ll just have to crash.  Tom Hillstrom quit, went to Met Council, and is now back with Xcel as contractor, is he in on this?  Better check with “Hilly” too!

Where’s the Hampton substation?  As you approach from the south on Hwy. 52, north of Hwy. 50, there’s this ugly Corten steel “Gateway to the Metro” of transmission towers, with the Hampton on the west side, at 215th Street — can’t miss it:

20140411_150009_resized

20140411_150213_resized

DSCN0155

Scoping Mtg. TOMRROW – Rochester Gas Pipeline

Filed under:Laws & Rules,News coverage,Nuts & Bolts,Upcoming Events — posted by admin on February 28, 2016 @ 8:13 pm

Map

Tomorrow it’s a meeting or two about a pipeline, but that’s not all… it’s about a gas plant at the beginning of this pipeline route!

First the pipeline — Minnesota Energy Resources Corporation is the applicant, and it’s PUC Docket 15-8858, a docket for a pipeline route on the west and southern edges of Rochester, Minnesota, starting at the “Westside” substation on the west side of town, along the big gas transmission pipeline that runs parallel with Hwy. 14.  From there it goes a section west, and then south and around to the east.

mtg

Meeting Presentation for tomorrow

And lo and behold, last week, Rochester Public Utilities announced its long planned natural gas generating plant for that same location as this pipeline starts, at 19th St. NW and 60th Ave. N. W.  This proposed plant was at issue during the CapX 2020 Transmission Certificate of Need docket, where RPU discussed building a natural gas plant in its RPU_34945_Report_June_2005.  Here’s the 2015_update_rpu_infrastructure_study.  During the CapX 2020 CoN hearing, that notion was pooh-poohed, but we knew better.  And voila, here it is!

First they brought it up at RPU Board meetings over the summer:

PUB- Resolution 4315 – Resolution: West Side Energy Station

Westside Energy Station Epc – Bids in Minnesota

And finally, last week, RPU made it’s plans to add new natural gas generation VERY public:

A New Generating Station for Rochester

Back in that CapX 2020 Certificate of Need proceeding (PUC Docket 06-1115) it was an issue because the “need” used to justify CapX 2020 transmission to Rochester was so very small that it could be met with this RPU planned natural gas plant.  Here’s what I wrote in the 2008 No CapX 2020 Initial Brief:

Most importantly, the need is overstated. In addition to modeling performed with all local generation off line, infrastructure planned was not considered. For example, in Rochester, there are FOUR 161kV lines planned that were not taken into consideration, and which could well serve Rochester’s needs. In addition, RPU, the Rochester utility, has planned for new generation at the West Side substation (Ex. 100, lower left corner), where two of those four lines will be connection to serve Rochester. Ex. 157, Report on the Electric Utility Baseline Strategy for 2005-2030 Electric Infrastructure, June 2005, Summary p. S-21-S-22. Specifically, this report recommends actions that have been taken by RPU, resulting in the Westside Substation and transmission from it to serve the city:

Consider taking options on approximately 100 acres of land within the RPU service territory near a high pressure gas line and transmission facilities under RPU control for installation of future combustion turbine capacity.

…Around 2014, assuming that new generation is required in accordance with the long range plan and that generation has not been installed in connection with the transmission issue, begin the process for installation of approximately 50-100MW of natural gas-fired generation for an inservice date of 2018. The generation should be low capital cost with as low an operating cost as is consistent with expected operating capacity factors.

Id.

Local load as a reason for CapX is not supported by the evidence. The need, even if assumed, can be met in other ways, and these small amounts, if assumed in its entirety, cannot justify a project of this size.

And here we are, deja vu all over again.  Guess we need to make sure that phased and connected actions are considered in this pipeline environmental review.

And another thing, this pipeline environmental review — the PUC, despite that Sandpiper case, ordered a “comparative environmental analysis.”

PUC_Order – February 3, 2016, PUC eDockets #20162-117966-01

Nope, that “environmental review lite” is NOT sufficient…

Xcel’s bogus demand forecast basis for CapX

arrowdownRemember Xcel’s CapX 2020 peak demand projections of 2.49% annual increase?  How wrong can they be?  And how unjustified was their basis for a Certificate of Need for CapX 2020?  And how are they held accountable for those gross misrepresentations?  But now it’s time to pay, and who will pay?  This is why the rate case in progress, PUC Docket 15-826, is so important.

On the other hand, I love it when this happens… Xcel Peak Demand is again DOWN!  There’s a trend, and it’s called decreased demand.  Demand has yet to exceed the 2007 peak, and now it’s 8 years…

XcelPeakDemand2000-2015

Here’s the Xcel Energy SEC 10-K filed a couple days ago:

2015 – Xcel Energy 10-K

Is it any wonder they want to get away from a cost based rate a la their “e21 Initiative” scheme?  Particularly now that the bill for CapX 2020 is coming due and their newest rate case (PUC Docket GR-15-826) is now underway?

And the specifics, and note how they inexplicably forecast a 2016 peak of 9,327, which is based on a “normal weather conditions” assumption:

2015-Xcel Peak Demand Chart


next page