MISO bars access to planning meetings

From the public meeting materials, here’s what they’re looking at, above.  These are significant additions to the transmission grid in Minnesota and Wisconsin.  Look at the number of double circuits they want to add, and look at the new transmission planned for Minnesota and WIsconsin.  And note how, as with CapX 2020, it’s starting in the coal fields of the Dakotas.

MISO’s Economic Planning Users Group is planning a “Regional Transmission Overlay Study” and they’re having another meeting tomorrow, May 25, 2017 down in Metatairie, Louisiana.

Here’s the call in info:

WebEx Information
Event Number: 966 575 350
WebEx Password: Ts824634

Participant Dial-In Number: 1-800-689-9374
Participant Code: 823713

Meeting Materials from the MISO site:

Here’s the problem — they close the meeting, and people like me aren’t allowed to attend.  First I was told, back in January when I tried to register:

Thank you for registering for the Economic Planning Users Group (EPUG) on Jan 31.  The afternoon portion of this meeting will be held in CLOSED session and reserved from MISO Members or Market Participants only.  Please feel free to attend the morning session from 11:00 am to 12:45 pm ET / 10:00 am to 11:45 CT.

I filled out their “CEII – Non-Disclosure Agreement” form and fired it off.  But noooooo…

So next I went to the PUC’s Quarterly MISO update, where I was assured that we could make arrangements so that I could attend.  I resent the “CEII – Non-Disclosure Agreement” and went back and forth and it came to this (click for larger version).  Note this “explanation” of options to be able to attend:

The reason that you were not permitted to attend the closed session is because the meeting involved discussion of Critical Energy Infrastructure Information (CEII) and CEII access requests by Non-Member Individuals requires FERC clearance.  Another access option is to be included on Appendix A of a MISO member or Market Participant.

So that says there are two ways to gain access, 1) get “FERC clearance” or 2) “Another access option is to be included on Appendix A of a MISO member or Market Participant.“  One or the other. Emphasis added.  Here’s the email (click for larger version) laying out those two options:

Oh, I says to myself, off to FERC.  I sent in the requisite paperwork to FERC, and got “FERC clearance” and they shipped me the CEII information, including but not limited to the map.  I let MISO know I’d obtained “FERC clearance,” and here’s the response (click for larger version):

ARRRRGH, they have my CEII NDA on file, have had it since January 23, 2017.  I resent it to the writer of these emails on March 4, 2017, and I sent it again today, and objected to yet another change in their “rules” (click for larger version):

So the plot thickens — from MISO (click or larger version):

And from moi (click for larger version):

Xmsn Overlay coming soon to a backyard near you!

It’s early, so now’s the time to get agitated, get activated!

As if CapX 2020 wasn’t enough, and during the CapX 2020 Certificate of Need proceeding, word of the “JCSP” overlay came out.  And we know that Xcel, in its e21 Initiative, is whining about the grid only being 55% utilized (DOH! Because CapX and other transmission expansion wasn’t needed, was built, and now they’re trying to make us pay for it!).

And as if Obama’s RRTT wasn’t enough, now there’s this, check out Executive Order 13766:

Expediting Environmental Reviews and Approvals for High Priority Infrastructure Projects

And so now the rest of the story — here’s what they’re planning:

Here’s the list, in a spreadsheet:

20170131 EPUG Preliminary Overlay Ideas List

The Minnesota Public Utilities Commission has scheduled the MISO Utilities Quarterly Update Meeting for the Second Quarter of 2017 for Friday, March 3, 2017 from 10:00 AM to Noon in the Commission’s Large Hearing Room, 121 7th Place East, Suite 350, St. Paul, MN 55101.

MISO Q letter 03-10-2014.bh.-1

Note this part, to be discussed at this meeting:

Laying the ground work now for this, a huge build-out that isn’t needed, an overlay on top of transmission that wasn’t needed either.  NO!

SD Coal Connection Announced

Filed under:News coverage,South Dakota,Upcoming Events — posted by admin on February 24, 2013 @ 4:47 pm

transmission_towers =coal

.

Finally, the South Dakota to Minnesota transmission line is announced.

Transmission equals coal, the “benefits” of transmission are realized when coal displaces natural gas, when coal can be shipped anywhere:

ICF – MISO Benefits Analysis Study

And that can only happen with a massive transmission build-out, the likes of which we’re seeing with CapX 2020, and with a 765kV transmission web waiting in the wings:

RGOS – Regional Generation Outlet Study

We weren’t allowed to address coal and transmission lines from the Dakotas to Minnesota in the CapX Certificate of Need proceeding, even though their own map shows the full plan, from the Dakotas to Madison, yes, old news, but here we go again — see those transmission lines starting in the Dakotas?

ex-13-capx2020-powerpoint-p-7-big-picture-map

Finally, they’ve announced the South Dakota transmission lines, in this case, from Ellendale, SD to Big Stone, SD:

$300 million transmission line project to be discussed

By Jeff Natalie-Lees, jnatalie-lees@aberdeennews.com

11:16 p.m. CST, February 23, 2013

One of the largest electrical transmission line projects proposed in years will be discussed at five open house meetings this week.

The line from Big Stone City to Ellendale, N.D., would cover 150 to 175 miles and cut across land owned by several hundred farmers. The cost is estimated at $300 million to $340 million.

“It is definitely one of the biggest ones we have participated in,” said Mark Hanson, spokesman for Montana-Dakota Utilities.

The line, which would be jointly operated by Montana-Dakota Utilities and Otter Tail Power Company, would provide many benefits to the region, including providing transmission capacity for wind energy.

The meetings are designed to allow people to see the proposed corridors for the line and ask questions.

“We will be taking all this feedback from landowners and agencies and developing a preferred route,” Hanson said. “That is what we need when we file the route permit with the South Dakota and North Dakota public utilities commissions.”

Construction on the line would begin in 2016 and take three years to complete. In the meantime, the utilities will be working on securing easements from landowners and completing permits.

Landowners who sign an easement will receive a one-time payment for purchase of land at pole sites, Hanson said. The poles will be between 700 feet to 1,200 feet apart.

While precautions will be made to avoid damaging any crops during the construction of the poles and lines, landowners will be compensated for any damage, Hanson said.

The line has been recommended by the Midwest Independent Transmission System Operator, the independent regulatory agency for electrical transmission in 15 states and parts of Canada, as a “multivalue project.”

A study determined the need for the the line, Hanson said, and provide benefits such as:

While landowners are the most affected by the transmission line, everyone is invited to the meetings to learn more about the project, Hanson said.

Meetings

Open House meetings are scheduled in the following towns:

Groton: 5:30 to 7 p.m. Monday, Groton Area School; presentation at 6 p.m.

Ellendale, N.D.: 11:30 a.m. to 1 p.m. Tuesday, Fireside Restaurant and Lounge; presentation at noon.

Britton: 5:30 to 7 p.m. Tuesday, Britton-Hecla High School; presentation at 6 p.m.

Webster: 11:30 a.m. to 1 p.m. Wednesday, The Galley; presentation at noon.

Milbank: 5:30 to 7 p.m. Wednesday, Milbank Visitors Center; presentation at 6 p.m.

So why did it take so long?  Looks like it’s timed to begin as Minnesota ends…

doh




image: detail of installation by Bronwyn Lace