Quacks like a conflict…

Filed under:Cardinal-Hickory,News coverage,Nuts & Bolts,RUS EIS — posted by admin on December 12, 2018 @ 11:20 am

Looks like a conflict, quacks like a conflict, but maybe it’s just a duck?  A duck following the money?

ELPC in the news:

“It doesn’t fully do what’s required … which is to rigorously explore and objectively evaluate all reasonable alternatives,” said Howard Learner, executive director of the Environmental Law and Policy Center. “It assumes that a huge and expensive interstate transmission line must be built and doesn’t fully and fairly evaluate all reasonable alternatives.”

Here’s the full article:

Power line opponents pan draft review of Dubuque-Middleton transmission project

Here are links to the USDA RUS EIS:

RUS EIS for Cardinal-Hickory Creek released!

Let’s think about this… it’s hard to wrap my head around… Howard Learner opposing a transmission project?  After all the dough Environmental Law and Policy Center got to promote transmission?  Remember the transmission love fest held by ELPC where transmission opponents were not allowed to attend??

Here’s the press release from the ELPC site:

New Environmental Study of Proposed Cardinal-Hickory Creek Transmission Line Improperly Rejects Alternatives

FOR IMMEDIATE RELEASE:

Chuck Tenneson, charles@driftlessconservancy.org, 608-930-3252

Sarah Eddy, seddy@elpc.org, 312-795-3710

DODGEVILLE, Wis., Dec. 10, 2018 – The draft environmental impact statement (EIS) released recently by the U.S. Department of Agriculture’s Rural Utilities Service (RUS) for the proposed Cardinal-Hickory Creek transmission line includes only a cursory review of non-transmission alternatives to the high-voltage line such as greater energy efficiency, local renewables, and energy storage, despite requirements in federal law that alternatives be considered thoroughly. The draft EIS admits that non-transmission alternatives, along with lower-voltage and underground alternatives, were “not carried forward for detailed analysis.”

The proposed Cardinal-Hickory Creek transmission line in southwest Wisconsin would cut a swath through the state’s scenic and ecologically unique Driftless Area. The cost of the project would be borne by electric ratepayers in Wisconsin and other states and energy experts have concluded that the new transmission line is not needed due to flattened demand for electricity in Wisconsin and recent advances in energy technology.

The costs and environmental damage that would be created by the transmission line has sparked opposition and legal challenges from local grassroots citizens and conservation groups. Wisconsin’s Dane and Iowa Counties voted to oppose the transmission line and have intervened in the Public Service Commission proceedings to fight the project.

“We wouldn’t think of putting a power line across the Grand Canyon, so why would we think of putting one through one of the most beautiful and unique landscapes in the Upper Midwest?” Said Dave Clutter, executive director of the Driftless Area Land Conservancy. “We have a national treasure in the Driftless Area, and we should treat it like one.”

“RUS is required by federal law to ‘rigorously explore and objectively evaluate all reasonable alternatives’ to proposed transmission lines like the Cardinal-Hickory Creek project,” said Howard Learner, one of the Environmental Law and Policy Center attorneys representing DALC. “RUS cannot simply look at different environmentally harmful routes for this huge transmission line and call it a day.”

“Iowa County residents have come together to adamantly oppose this unneeded high-voltage power line, which would irreversibly damage the landscape, ecology, and recreation economy we depend on,” said Betsy D’Angelo, a member of the Driftless Defenders’ leadership team. “There are alternatives that can improve our electric system without damaging the Driftless Area’s most important natural areas.”

“The draft environmental impact statement for the Cardinal-Hickory Creek project ignores the reality of new technology that has improved energy efficiency and decreased the demand for electricity,” said David Meylor, chairman of the Western Dane Preservation Campaign, the Mount Horeb area citizens group formed to oppose the line. “Recent analyses of electric demand demonstrate that the expensive, invasive Cardinal-Hickory Creek transmission line project simply isn’t needed.”

“The proposed Cardinal-Hickory Creek Transmission line will have a significant negative impact on fish and wildlife habitat and the management of public lands in Southwestern Wisconsin and in light of other energy alternatives should not be constructed,” stated George Meyer, Executive Director of the Wisconsin Wildlife Federation.

The proposed Cardinal-Hickory Creek transmission line would install towers of up to 175-feet along a 100-mile route that would affect sensitive natural areas and disrupt economic activity. The project could cost ratepayers more than $1 billion during the life of the project, including a profit margin for the transmission line’s utility owners that is guaranteed by Wisconsin law.

Legal counsel for the Driftless Area Land Conservancy will be reviewing the RUS’s draft EIS in greater detail and will submit comprehensive public comments to the agency. Members of the public are strongly encouraged to submit comments before the deadline of Feb. 5, 2019.

###

Issued by:

Driftless Area Land Conservancy

Driftless Defenders

Environmental Law and Policy Center

Western Dane County Preservation Campaign

Wisconsin Wildlife Federation

MISO bars access to planning meetings

From the public meeting materials, here’s what they’re looking at, above.  These are significant additions to the transmission grid in Minnesota and Wisconsin.  Look at the number of double circuits they want to add, and look at the new transmission planned for Minnesota and WIsconsin.  And note how, as with CapX 2020, it’s starting in the coal fields of the Dakotas.

MISO’s Economic Planning Users Group is planning a “Regional Transmission Overlay Study” and they’re having another meeting tomorrow, May 25, 2017 down in Metatairie, Louisiana.

Here’s the call in info:

WebEx Information
Event Number: 966 575 350
WebEx Password: Ts824634

Participant Dial-In Number: 1-800-689-9374
Participant Code: 823713

Meeting Materials from the MISO site:

Here’s the problem — they close the meeting, and people like me aren’t allowed to attend.  First I was told, back in January when I tried to register:

Thank you for registering for the Economic Planning Users Group (EPUG) on Jan 31.  The afternoon portion of this meeting will be held in CLOSED session and reserved from MISO Members or Market Participants only.  Please feel free to attend the morning session from 11:00 am to 12:45 pm ET / 10:00 am to 11:45 CT.

I filled out their “CEII – Non-Disclosure Agreement” form and fired it off.  But noooooo…

So next I went to the PUC’s Quarterly MISO update, where I was assured that we could make arrangements so that I could attend.  I resent the “CEII – Non-Disclosure Agreement” and went back and forth and it came to this (click for larger version).  Note this “explanation” of options to be able to attend:

The reason that you were not permitted to attend the closed session is because the meeting involved discussion of Critical Energy Infrastructure Information (CEII) and CEII access requests by Non-Member Individuals requires FERC clearance.  Another access option is to be included on Appendix A of a MISO member or Market Participant.

So that says there are two ways to gain access, 1) get “FERC clearance” or 2) “Another access option is to be included on Appendix A of a MISO member or Market Participant.“  One or the other. Emphasis added.  Here’s the email (click for larger version) laying out those two options:

Oh, I says to myself, off to FERC.  I sent in the requisite paperwork to FERC, and got “FERC clearance” and they shipped me the CEII information, including but not limited to the map.  I let MISO know I’d obtained “FERC clearance,” and here’s the response (click for larger version):

ARRRRGH, they have my CEII NDA on file, have had it since January 23, 2017.  I resent it to the writer of these emails on March 4, 2017, and I sent it again today, and objected to yet another change in their “rules” (click for larger version):

So the plot thickens — from MISO (click or larger version):

And from moi (click for larger version):

RUS’ Cardinal-Hickory Creek meetings

Filed under:Cardinal-Hickory,Laws & Rules,News coverage,Nuts & Bolts,RUS EIS,Upcoming Events,Wisconsin — posted by admin on December 7, 2016 @ 7:16 am

20161206_1655071

Slow evening at Rural Utilities Service’s (RUS) scoping meeting for the Environmental Impact Statement for the Cardinal – Hickory Creek transmission project.  RUS is involved because Dairyland Power Cooperative (DPC) plans to hold a 9% undivided interest in the project, and are looking to RUS to provide the funding.  RUS held two more meetings, following on prior meetings October 31 and November 1 & 2, because their notice for those meetings went out a day late, so another Notice went out:

Notice of Intent To Hold Public Meetings and Prepare Environmental Impact Statement (October 18, 2016

Second Notice_2016-27988-2

Where’s my prior post on these meetings?  It’s gone! Here’s the dates and locations (click for larger version) — the last one is tomorrow in Barneveld, Wisconsin:

noice12-6-7-2016

So to make quick work of it, this is cut and pasted from the RUS Cardinal Hickory Creek page:

I had a quick chat with Dennis Rankin who’s in charge of the environmental review on this and the Dairyland Q-1 South projects, and had a few quick things to register, particularly that ATC has announced that the project is delayed:

ATC postpones Cardinal-Hickory Creek project – The Dodgeville Chronicle -Dodgeville, WI

I had this article and a few comments to add tonight, and will file more detailed comments before the deadline — now January 6, 2017.

Overland-Legalectric Preliminary Comments Cardinal-Hickory Creek(don’t worry, I’ll get this looking pretty by the deadline!)

20161206_1654551

On the way in, there was new transmission marching across the countryside, so ugly:

xmsn-mvp

And look how close to this house in New Vienna, right up near the garage, and not far from the house either — this line cut right through the middle of town:

20161206_1550331

20161206_1551041

newvienna1

But all in all, it was a beautiful day for a drive today!

20161206_1543442

CapX 2020 files going into recycling & dumpster…

Filed under:Cost Recovery,Hampton-Alma-LaCrosse,Nuts & Bolts,Reports - Documents,Upcoming Events — posted by admin on September 18, 2016 @ 3:08 pm

rocktenn

The CapX 2020 project has been a part of my life for over 12 years… and now it’s mostly up and running.  So I’ve spent the day digging through the dusty files.  What a mess.  Boxes and boxes and boxes.

Image result for CapX 2020

That’s a map from 2007 or so with coal plants ID’d from the MISO queue, some up and running, many not (good!).  The north/south line along the MN and ND/SD border is missing.  The North Dakota, South Dakota and Wisconsin legs are all permitted too, much constructed.  Well played, Xcel.

During the Certificate of Need proceeding, we were not able to address the bulk power transfer aspect of this, because after all, “it terminates in Wisconsin.”

terminatelax

Meanwhile, Xcel Energy’s rate case based on its e21 Initiative whines that the grid is only 55% utilized!

55

You’re not going to be efficient if you’re reliant on massive transmission lines, DOH!  Oh well, we knew all this, and yet here we are, billions of dollars of “wires in the air” and the bills just now arriving.  Xcel argued that No CapX 2020 should be excluded:

miso-mvp

But CapX 2020’s Minnesota Brookings – Hampton transmission line is part of MISO’s MVP 17 project portfolio!  DOH!  And the judge apparently missed that Xcel brought up both CapX 2020 cost recovery and MISO MVP cost recovery in their direct testimony!

Oh, but it doesn’t end there…

No CapX 2020 was not allowed to intervene in the rate case and address transmission recovery, after all, the permits have been granted, so WHY DOES NO CAPX EVEN EXIST?!?!?  So said the judge:

objection1

Oh well…

Remember their shindig on Tuesday:

September 26, 2016

Time?  They’re not telling…

Hampton Substation

Highway 52 and 215th Street (N. of Hwy. 50)

 

Scoping Mtg. TOMRROW – Rochester Gas Pipeline

Filed under:Laws & Rules,News coverage,Nuts & Bolts,Upcoming Events — posted by admin on February 28, 2016 @ 8:13 pm

Map

Tomorrow it’s a meeting or two about a pipeline, but that’s not all… it’s about a gas plant at the beginning of this pipeline route!

First the pipeline — Minnesota Energy Resources Corporation is the applicant, and it’s PUC Docket 15-8858, a docket for a pipeline route on the west and southern edges of Rochester, Minnesota, starting at the “Westside” substation on the west side of town, along the big gas transmission pipeline that runs parallel with Hwy. 14.  From there it goes a section west, and then south and around to the east.

mtg

Meeting Presentation for tomorrow

And lo and behold, last week, Rochester Public Utilities announced its long planned natural gas generating plant for that same location as this pipeline starts, at 19th St. NW and 60th Ave. N. W.  This proposed plant was at issue during the CapX 2020 Transmission Certificate of Need docket, where RPU discussed building a natural gas plant in its RPU_34945_Report_June_2005.  Here’s the 2015_update_rpu_infrastructure_study.  During the CapX 2020 CoN hearing, that notion was pooh-poohed, but we knew better.  And voila, here it is!

First they brought it up at RPU Board meetings over the summer:

PUB- Resolution 4315 – Resolution: West Side Energy Station

Westside Energy Station Epc – Bids in Minnesota

And finally, last week, RPU made it’s plans to add new natural gas generation VERY public:

A New Generating Station for Rochester

Back in that CapX 2020 Certificate of Need proceeding (PUC Docket 06-1115) it was an issue because the “need” used to justify CapX 2020 transmission to Rochester was so very small that it could be met with this RPU planned natural gas plant.  Here’s what I wrote in the 2008 No CapX 2020 Initial Brief:

Most importantly, the need is overstated. In addition to modeling performed with all local generation off line, infrastructure planned was not considered. For example, in Rochester, there are FOUR 161kV lines planned that were not taken into consideration, and which could well serve Rochester’s needs. In addition, RPU, the Rochester utility, has planned for new generation at the West Side substation (Ex. 100, lower left corner), where two of those four lines will be connection to serve Rochester. Ex. 157, Report on the Electric Utility Baseline Strategy for 2005-2030 Electric Infrastructure, June 2005, Summary p. S-21-S-22. Specifically, this report recommends actions that have been taken by RPU, resulting in the Westside Substation and transmission from it to serve the city:

Consider taking options on approximately 100 acres of land within the RPU service territory near a high pressure gas line and transmission facilities under RPU control for installation of future combustion turbine capacity.

…Around 2014, assuming that new generation is required in accordance with the long range plan and that generation has not been installed in connection with the transmission issue, begin the process for installation of approximately 50-100MW of natural gas-fired generation for an inservice date of 2018. The generation should be low capital cost with as low an operating cost as is consistent with expected operating capacity factors.

Id.

Local load as a reason for CapX is not supported by the evidence. The need, even if assumed, can be met in other ways, and these small amounts, if assumed in its entirety, cannot justify a project of this size.

And here we are, deja vu all over again.  Guess we need to make sure that phased and connected actions are considered in this pipeline environmental review.

And another thing, this pipeline environmental review — the PUC, despite that Sandpiper case, ordered a “comparative environmental analysis.”

PUC_Order – February 3, 2016, PUC eDockets #20162-117966-01

Nope, that “environmental review lite” is NOT sufficient…

Tuesday night in Onalaska

Filed under:BadgerCoulee - Wisconsin,Laws & Rules,Nuts & Bolts,Q-1 Upgrade,Wisconsin — posted by admin on December 17, 2015 @ 9:55 pm

20151215_185850[1]

AS you scroll down, keep in mind the tremendous job that the City of Onalaska did presenting their case in the Badger Coulee transmission docket (go HERE and search for docket 05-CE-142, and look for Onalaska filings).

Grace – Direct Testimony

Tuesday night, the Onalaska Plan Commission took up the revised Comprehensive Plan.

Onalaska Comprehensive Plan Final Draft – 12-07-2015

Here’s where you can check out the new Comprehensive Plan (search for “transmission” and you’ll find not much):

City of Onalaska 2015 Comprehensive Plan Page

The current Zoning map (click for larger version):

MAP_Current_Onalaska_Comp_Plan_Report_12-07-2015Future:

MAP_Future_Onalaska_Comp_Plan_Report_12-07-2015

Do you see any transmission lines on that map?  Any pipelines on that map?  The City doesn’t have a map of transmission lines, or pipelines, yet it’s a prominent feature of Onalaska, just drive up Hwy 35 or Hwy 53 and you’ll see what I mean.  The City Land Use & Development Director said in the meeting that they don’t have one, it would be very difficult to put together and that this info can be regarded as “proprietary.”  Not quite, it could be “CEII” information, but when you see it driving down the road, when you look at google and there it is, there’s no reason the City can’t draw a line on the map!

There’s a lot of transmission through Onalaska, lining both sides of the highways, in the middle of the city bottlenecked in-between the river and the bluffs (like Red Wing), and it runs right through the heart of the city.  Here’s ATC’s “map” of transmission:

Onalaska_xmsn

Here’s WI-PSC’s map:

PSC Xmsn Map As you can see, it’s not rocket science to put a map together of transmission through Onalaska and its potential expansion areas.

Dairyland is wanting to tear down its old line on the west side of Highways 53 and 35 and virtually double the height of the towers and the capacity.  That’s not updating or maintenance, that’s “tear down the old line and build a new one” construction.

NOW is the time, because there’s not yet a Dairyland application, and because Xcel’s line on the east side of Highways 35 and 53 is also old, they’re going to want to “upgrade” soon too.  The routing of transmission through Onalaska in light of Wisconsin’s adoption of its Electrical Code which prohibits construction under a line, means that new construction should be carefully reviewed.  And right now, rebuilding, tearing down and new construction of something much bigger, shouldn’t be allowed over and next to homes and businesses.  What to do?  It’s a narrow area with a lot of transmission!  But this is what “planning” is all about.  Looking into the future and figuring out what they want the City to look like, how they can address the extreme impacts of transmission, and if they can minimize or mitigate these impacts.  Here’s an example of it running through people’s back yards, stars indicate pole placement in people’s back yards, and the white/red lines are access roads through people’s back yards!

10th AveN

On behalf of No CapX 2020, I sent the Planning Commission and City Council these comments:

NoCapX2020 Comment_OnalaskaCompPlan

At Tuesday’s meeting, there were few commenters, and they quickly wrestled with the issues raised, and sent it back to the Committee for consideration of transmission issues and impacts.

THANK YOU, ONALASKA PLAN COMMISSION!

Annual Hearing for Power Plant Siting Act 12/1

Filed under:Nuts & Bolts,PUC Docket,Upcoming Events — posted by admin on November 13, 2015 @ 8:50 am

NSP_Stack

I’m having a difficult time getting worked up about the PPSA Annual Hearing this year.  It’s the time we have to tell the Commission what does and does not work with the Power Plant Siting Act.  I’ve been at this for 20 years now, and it never ends, doesn’t change, so many of the same problems, over and over.  It is SO hard for people to participate and while it got better for a while, when people stood up and leveled the playing field, and with Gov. Ventura’s active outreach to the public, well, can’t have that happen, so then NSP’s big buck lobbyists changed the laws to their advantage (2001) and then bought off the funded intervenors and they rewrote the laws together (2003 & 2005) and now the head of one of those funded intervenors, the Waltons, is at Commerce in charge of utility permitting (CoN and Route/Siting) and another on the Commission.

Oh well, it’s that time again… Let’s all put this on our calendar and once more, with feeling, tell them what we really think!

+++++++++++++++++++++++++++++++++++++

Notice of the Power Plant Siting and Transmission Line Routing Program Annual Hearing

Issued: November 6, 2015

In the Matter of the 2015 Power Plant Siting Act Annual Hearing

Public Utilities Commission (PUC) Docket Number: E999/M-15-785

Office of Administrative Hearings (OAH) Docket Number: 60-2500-32901

Date: Tuesday, December 1, 2015

Time: 9:30 a.m.

Location: Minnesota Public Utilities Commission, Large Hearing Room, 121 7th Place East, Suite 350, Saint Paul, MN 55101

Bad weather? Find out if a meeting is canceled. Call (toll-free) 1-855-731-6208 or 651-201-2213 or visit mn.gov/puc

Hearing Description

The annual hearing is required by Minnesota Statute § 216E.07, which provides that:

Thecommission shall hold an annual public hearing at a time and place prescribed by rule in order to afford interested persons an opportunity to be heard regarding any matters relating to the siting of large electric generating power plants and routing of high-voltage transmission lines. At the meeting, the commission shall advise the public of the permits issued by the commission in the past year….

Note – No decisions about specific projects are made at the annual hearing.

Public Hearing Information

  • Public hearings start on time.
  • Arrive a few minutes early so you have time to sign in, pick up materials, and find a seat.
  • Administrative Law Judge James LaFave will preside over the hearing.
  • Public Utilities Commission and Department of Commerce staff members are available to answer questions about the Power Plant Siting Act processes and the projects.
  • You may add verbal comments, written comments, or both into the record.
  • Learn more about participating at a public hearing at http://mn.gov/puc/resources/meetings-and-hearings.jsp
  • Judge LaFave will use information gathered at the public hearing and during the comment period to write a summary report for the Commission

Submit Comments

Topics for Public Comment:

  • Any matters related to the site permit process for large electric generating power plants and routing of high-voltage transmission lines.

Comment Period: November 6, 2015 through January 5, 2016 at 4:30pm.

  • Comments must be received by 4:30pm on the close date
  • Comments received after comment period closes may not be considered

Online Visit mn.gov/puc, select Speak Up!, find this docket (15-785), and add your comments to the discussion.

If you wish to include an exhibit, map or other attachment, please send your comments via eFiling (see below) or U.S. Mail.

Please include the Commission’s docket number in all communications.

Filing Requirements: Utilities and state agencies are required to file documents using the Commission’s electronic filing system (eFiling). All parties, participants and interested persons are encouraged to use eFiling: mn.gov/puc, select eFiling, and follow the prompts.

Important Comments will be made available to the public via the Public Utilities Commission’s website, except in limited circumstances consistent with the Minnesota Government Data Practices Act. The Commission does not edit or delete personal identifying information from submissions.

Hearing Agenda

I. Introductions
II.Overview of Programs
A. Public Utilities Commission – Facilities Permitting and Public Advisor
B. Department of Commerce – Energy Facilities Permitting Unit
C. Role of Other Agencies
III. Projects Reviewed
A. Projects Permitted in 2015
B. Pending and Anticipated Projects
C. Electric Facilities Subject to Power Plant Siting Act
1. Generating Plants
2. Transmission Lines
IV. Public Questions and Testimony
V. Adjourn

How to Learn More

Subscribe to the Docket: Subscribe to receive email notifications when new documents are filed. Note – subscribing may result in a large number of emails.

  1. mn.gov/puc
  2. Select Subscribe to a Docket
  3. Type your email address
  4. For Type of Subscription, select Docket Number
  5. For Docket Number, select 15 in the first box, type 785 in the second box
  6. Select Add to List
  7. Select Save

Full Case Record: See all documents filed in this docket via the Commission’s website – mn.gov/puc, select Search eDockets, enter the year (15) and the docket number (785), select Search.

Project Mailing Lists: Sign up to receive notices and opportunities to participate in other dockets relating to specific projects in which you are interested (meetings, comment periods, etc.). Contact docketing.puc@state.mn.us or 651-201-2234 with the docket number, your name, mailing address and email address.

Minnesota Statutes and Rules: The hearing is being conducted according to Minnesota Statute 216E.07. Minnesota Statutes are available at www.revisor.mn.gov.

Project Contacts

Public Utilities Commission Public Advisor

Tracy Smetana – consumer.puc@state.mn.us, 651-296-0406 or 1-800-657-3782

Q-1D South Comment Period Extended!

Filed under:BadgerCoulee - Wisconsin,Nuts & Bolts,Q-1 Upgrade,RUS EIS,Wisconsin — posted by admin on October 2, 2015 @ 11:17 am

SUCCESS!!!  But… but… but only extended by 10 days…  HUH?  We still don’t have much to go on here, and major details like the capacity of this project, well, they’re still leaving us in the dark.

Here’s the new info posted on the Dairyland Power Cooperative site:

 

Compare the posted Corridor Map with the ones I’d received a couple weeks ago, note how much is M-I-S-S-I-N-G!

Appendix_A_Q1D_South_Sheetmap_150616_June 2015

The most obvious thing missing is the access roads, every single one of them.  What else?

And look what’s added.  I think the big difference is that this is “environmental” information, based on the subjects they listed in their first notice, like prime farmland, wetlands, etc.  It’s not the construction/technical layer.  So by looking at these new maps, we get the picture of what they think impacts are, and we can at least get a feel for that.

On the first map, there’s a brown area along the river/creek, but I can’t tell what color that would be on the legend… yellow?  On the third map, there’s a huge section with many different markings, covering the Wildlife Refuge.  H How would 95 – 115 foot tall towers this close to the ledge of the drop off into the Wildlife Refuge not have an impact on the protected (and unprotected!) migratory birds in this corridor?  What does the greatly increased tower height do to the viewshed from below on the Missisisppi?  They’re lowering towers and configuring horizontally for the La Crosse River Floodplain, so doesn’t this mean there are avian considerations?  And what about the Airport Overlay that limits structure height?

And check out this “Fact Sheet.”  Briggs Road to La Crosse Tap (Q-1D South) 161 kV Rebuild Project – Fact Sheet

Dairyland Power Cooperative says:

“Can you tell me about the Project?”  Well, not much, this is a two pager.  Focus is on using existing RoW.  Note they do point out existing and temporary access routes.  I would guess that this is something they’d have to have easements for… do they have easements?

“Why is the Project needed?”  They raise reliability problems, but these were addressed in the Badger Coulee, and the record there says Badger Coulee addresses these problems.  Oh, but it’s also impacting the fiber optic service on these structures.  Hmmmm, fiber optic.  Leased to who and for how much?  I don’t see any information on the fiber optic upgrade that would logically occur with upgrade of the electrical part of this line.  DISCLOSE PLEASE!

“What if the line is not rebuilt?”  This isn’t a rebuild, this is an upgrade.  Higher towers, from 45 – 85 feet now to 95-115 feet.  BIG DIFFERENCE!  Capacity?  Who knows, they’re not telling me, but folks, I have some ideas, based on the MISO disclosure of use of 795 ACSS conductor.  This is conjecture, because I’m still waiting for information from Dairyland, with the 437 MVA Peak taken from prior docket info, and the 84 MVA Average as a low-ball number (because they always understate capacity).  Click on table for a larger version that’s not cut up by the sidebar on the right:

Q-1 161 kV 795 ACSS_ Calculated Magnetic Field

“How are environmental impacts considered?”  As they state, this is a financial project, they’re doing this for financing.  Financing approval is a “major governmental action.”  Think not, Dairyland?  RUS?  Let’s discuss it in the alley!  Dairyland’s blurb states that “RUS has determined that the project would require the preparation of an Environmental Report (ER) to analyze potential impacts to the natural and human environments.”  ER?  How does this not require an EIS?  How is an ER compliant with NEPA?  How is it that Dairyland is allowed to segment these Q-1 projects out and that Marshland – Briggs Road required a full blown EIS and this doesn’t?  IT’S ALL ONE PROJECT, this upgrading the Q-1 line!

Read their new documents carefully, and take a good look at the new maps, comparing with the other ones.  What’s your take?

As always in this, take a few seconds and ask for more information, and when you’ve reviewed this stuff disclosed today, send comments to:

  • Chuck Thompson, Manager, Siting & Regulatory Affairs, Dairyland Power Cooperative, 3200 East Avenue South, La Crosse, WI  54602-0617, or via email at cat@dairynet.com  (608) 787-1432.
  • Dennis Rankin, Engineering and Environmental Analyst,  USDA RUS, 1400 Independence SW, Mailstop 1571, Washington D.C., 20250-1571, or via email at dennis.rankin@wdc.usda.gov    (202) 720-1953

++++++++++++++++++++++++

Here’s the full blurb from Dairyland’s Chuck Thompson, hot off the press this morning:

Dairyland Power Cooperative is hereby extending the 30-day comment period related to prime farmlands, farmland of statewide importance, 100-year floodplains, wetlands, and other comments for the Q-1D South 161 kV rebuild.  Under this expanded period, comments should be submitted in writing to Dairyland Power Cooperative within 10 days of the publication of this notice.

Dairyland Power Cooperative, 3200 East Avenue South, La Crosse, WI 54602-0817, is planning to rebuild approximately nine miles of 161 kilovolt transmission line in La Crosse County (Q-1D South Project).  The Q-1D South Project begins just south of the Briggs Road Substation near the Village of Holmen and ends at the La Crosse Tap south of the La Crosse River near Keil Coulee Road. Constructed in the 1950s, the line is now in poor condition and reaching the end of its service life.  The rebuild will occur along the existing 161 kV alignment within the existing right-of-way.  It has been determined that the Project, as proposed, will be located in a prime farmlands, 100-year floodplain, and wetlands. The Project will occupy 126 square feet of prime farmland, 12.6 square feet of farmland of statewide importance, 63 square feet of 100-year floodplain, and 50.4 square feet of wetlands.

Dairyland Power Cooperative believes that there is no practicable alternative that will avoid locating the Project in prime farmlands, farmland of statewide importance, 100-year floodplains, and wetlands.  Additional information on the project can be found at:  http://www.dairynet.com/power_delivery/project_updates.php for sheet maps and a fact sheet.

Copies of all comments received will be forwarded to the U.S. Department of Agriculture Rural Utilities Service for consideration prior to approval of financing assistance or taking other Federal action related to the Project.

Send your comments to:  Chuck Thompson, Dairyland Power Cooperative, 3200 East Ave South,
La Crosse WI 54602 or email your comments to cat@dairynet.com.  

 

Comments sent on Q-1D South rebuild!

Filed under:BadgerCoulee - Wisconsin,Hampton-Alma-LaCrosse,Laws & Rules,News coverage,Nuts & Bolts,RUS EIS,Wisconsin — posted by admin on September 25, 2015 @ 1:47 pm

mailbox

SENT!  On behalf of No CapX 2020 I sent the following Comments:

No CapX 2020_Q-1D South_Comment_9-25-2015

I’ve asked how many times for more information, nada, still nothing.  N-O-T-H-I-N-G!

Of particular note is this handy-dandy chart that Bruce McKay had put together for the Brookings docket, and I plugged in the voltage, amps, MVA and here’s what we get for magnetic fields for various options of this 795 ACSS 161 kV transmission line — CLICK FOR A BIGGER VERSION, this is all that will fit in this format:

Q-1 161 kV 795 ACSS_ Calculated Magnetic Field

OK, Dairyland, USDA RUS — let’s see your calculations, let’s have disclosure of the peak and normal amps, the MVA, everything.  Show me this is wrong!  Note at what point mG levels drop to a 2-4 mG “safe” range.

For those of you who haven’t yet asked for an extension of time to comment, or who haven’t yet sent in comments, there’s still time, until 11:59 p.m. Sunday!

Send Comments, via email to BOTH:

  • Chuck Thompson, Manager, Siting & Regulatory Affairs, Dairyland Power Cooperative, 3200 East Avenue South, La Crosse, WI  54602-0617, or via email at cat@dairynet.com  (608) 787-1432.
  • Dennis Rankin, Engineering and Environmental Analyst,  USDA RUS, 1400 Independence SW, Mailstop 1571, Washington D.C., 20250-1571, or via email at dennis.rankin@wdc.usda.gov    (202) 720-1953

And who knows — with all the requests coming in, maybe they’ll extend the Comment period!!

Let us know, Chuck!

Book_Borchwriting

UPDATE: Dairyland’s Q-1 “upgrades” through La Crosse

Filed under:BadgerCoulee - Wisconsin,Hampton-Alma-LaCrosse,News coverage,Nuts & Bolts,RUS EIS,Wisconsin — posted by admin on August 30, 2015 @ 6:30 am

DairylandNotice

“Upgrade” through Holmen, Onalaska, La Crosse, from Briggs Road to some substation south of 90.

This is a “notice” found in the La Crosse Tribune on Friday.  Take a close look, yes, it’s hard to read, but multiple searches of the Notices section online have NOTHING, nada…

This is another USDA Rural Utilities Services project, yet here, there’s no indication of the status of the project, no RUS contact, and they want comments sent to DAIRYLAND, and we’re to trust they’ll send them to whoever.

Where’s the link to the USDA RUS site?  Where’s the link for the project application.  WHERE’S A DECENT MAP!!??!!??!!??

WHAT KIND OF NOTICE IS THIS?

$50 says it’s USDA’s Stephanie Strength on this project, as she was on the Dairyland Q-1D going north from Briggs Rd. to Marshaland, as she was on the Dairyland financing for its share of CapX 2020.

Any Comments you send to Dairyland’s Chuck Thompson, I’d advise you also send any comments or questions to (?? NOTE: Stephanie Strength’s two emails are NOT working… so who is Project Manager?):

Stephanie Strength, Project Mgr.

Dairyland Q-1D South Upgrade
USDA Rural Development Utilities Programs
1400 Independence Avenue SW, Room 2244
Mail Stop 1571
Washington, DC  20250-1571

… or by email:

stephanie.strength@wdc.usda.gov (doesn’t seem to be working!)

stephanie.strength@usda.gov

The map, for starters, is awful, can’t even see it, nothing identified but lines for a couple of major highways, but anyone in the area knows this line, running up and down Hwy 35. from near Briggs Road substation through Onalaska going south and darting with Xcel’s line on the other side, back and forth, through trailer parks, towards 90, across and then south.

This is what this line looks like, going right through people’s back yards, front yards, and over homes, directly overhead, right next to it, how can Dairyland think this should be “upgraded” — it should be torn down:

Kimberly St

And at Ulman St., there are two trailers right up against the structures:

Ulman_St[1]

It’s bad enough that Dairyland is planning this upgrade, but how does any city allow this to happen?  In what world is it OK to allow development under a transmission line?  On the other side of Hwy. 35 it’s the same thing, an Xcel transmission line over a trailer park.  This shows zero regard for human life.


next page