Incoming! Answers & Comments on FERC Complaint
Big CapX 2020 day today, what with oral arguments at the Appellate Court on Segment 1 and Segment 3 of the Minnesota routing docket, and LOTS of Answers and Comments due today on the FERC Complaint filed by CETF and SOUL regarding the CapX 2020 Hampton-La Crosse transmission project.
Here’s the Complaint:
And here are the Answers and Comments, the despondent Respondents first and then everyone else!
MISO Answer to Complaint EL13-49-000
MRO Answer to FERC Complaint EL13-49-000
Respondent Utilities Answer to FERC Complaint EL13-49-000
PSC Wisconsin Motion to Intervene – FERC EL13-49-000
MISO Transmission Owners Motion to Intervene – FERC EL13-49-000
Rochester Public Utilities Motion to Intervene – FERC EL13-49-000
Good reading on a cold spring night! Fire up that printer and start running the tub!
Pingback:No CapX 2020 » CETF/SOUL files Motion for Leave to Answer and Answer