PUC issues written orders in ITC docket

Filed under:ITC MN & IA 345 kV,Nuts & Bolts — posted by admin on November 25, 2014 @ 2:00 pm

gavel

It’s official!  Here are the Minnesota Public Utilities Commission Orders in the ITC Midwest MN/IA 345 kV Transmission Project case for their Certificate of Need and Route Permit — hot off the press:

Order_Certificate of Need_201411-104931-01

Order_Route Permit_14-0120_12-1337

Today the clock starts ticking.  If there’s anything that you, an “affected party” take issue with and want the Commission to reconsider, there is a 20 day window to file a Motion for Reconsideration.  That means you need to file it by December 15, 2014.

Not only is this relevant to the ITC docket, but as the first of the MISO MVP projects to come down the pike, it’s also relevant to the Badger Coulee docket now ongoing in Wisconsin (GO HERE and search for PSC Docket 05-CE-142) as the first MVP project in Wisconsin.

doh

Here’s the short version of the Certificate of Need Order:

Order_Short

Here are some issues for No CapX 2020 — this is the Commission’s interpretation — from the Certificate of Need Order:

1 2 3 4 5

So there ya have it!  Monday December 15, 2014 is the deadline for Motions for Reconsideration.

 

 

 

 

 

 

zero comments so far »