Dedication of CapX 2020?

Filed under:Brookings Routing Docket,Fargo-St Cloud,St.Cloud-Monticello — posted by admin on May 4, 2015 @ 3:35 pm

WHAT?!?!  The dedication ceremony for the CapX 2020 Brookings – Hampton and Fargo – St. Cloud – Monticello projects, and I didn’t get a gold engraved invitation?  And of course there’s Beth Soholt, “Wind on the Wires” (f/k/a a program of the Izaak Walton League) toadying for these projects — how much did Wind on the Wires get in grants to promote transmission?  Minnesota Department of Commerce represented as well, though it’s the Commissioner!  Why wouldn’t they send Beth’s old boss, Bill Grant, particularly given that he’s now Deputy Commissioner of Commerce!  It’s all connected, don’t cha know.

They say these are energized.  Wonder if/when they’re going to put transformers in?  Anyone know?

CapX Dedication Ceremony

How’s this for a quote, from the Forum:

The power buzzing in the transformers come from another power line that stretches west to the coal power plants in Center, N.D.

And the full article here: Xcel energizes new Fargo to St. Cloud powerline

Here’s the poop from KNSI News:

CapX2020 transmission lines celebrated

May 4, 2015 at 4:08 pm

ST. CLOUD, Minn. (KNSI) – A dedication ceremony was held today in St. Cloud to commemorate the completion of two high-voltage electric transmission lines — part of CapX2020. 

The CapX2020 Brookings County-Hampton and Fargo-St. Cloud-Monticello projects complete $1.3 billion worth of electric grid investment in Minnesota, North Dakota and South Dakota.

Will Kaul is chairman of CapX2020, a joint initiative of 11 transmission-owning utilities in Minnesota, the Dakotas and Wisconsin

“It’s just in time when the concern about the grid and the security and the resilience of the grid is very high … a time when the resource mix that is coming into play is in transition and new resources are coming online,” Kaul said.

The two projects took 11 years and were completed on time and without going over budget to provide reliable, affordable service to Minnesota and the surrounding region, while also expanding access to renewable energy, according to Teresa Mogensen of Xcel Energy.

“We compare our CapX2020 lines to another big project – the Vikings stadium – that’s a $1 billion investment, too,” said Mogensen, who provided some perspective.

The CapX2020 projects include four 345 kV transmission lines and one 230 kV line — the largest development of new transmission in the Upper Midwest in almost four decades.

One way the CapX2020 projects help keep prices low is by alleviating congestion on the system. When more electricity is needed in an area than the area’s transmission system can provide, electricity is dispatched from a different generation source that can serve the area, but at a higher cost.

 

 

zero comments so far »

Please leave a comment below!

Copy link for RSS feed for comments on this post or for TrackBack URI

Leave a comment

Line and paragraph breaks automatic, e-mail address never displayed, HTML allowed: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <s> <strike> <strong>

(required)

(required)




image: detail of installation by Bronwyn Lace