Tomorrow — Q-1D South Comments due!

Filed under:BadgerCoulee - Wisconsin,Wisconsin — posted by admin on September 24, 2015 @ 8:57 am

Sheet Map 3

Tomorrow is the deadline for Comments on Dairyland’s “Q-1D South” upgrade — technically it’s Sunday — but don’t wait until the last minute.

Send Comments to (I recommend via email):

  • Chuck Thompson, Manager, Siting & Regulatory Affairs, Dairyland Power Cooperative, 3200 East Avenue South, La Crosse, WI  54602-0617, or via email at cat@dairynet.com  (608) 787-1432.
  • Dennis Rankin, Engineering and Environmental Analyst,  USDA RUS, 1400 Independence SW, Mailstop 1571, Washington D.C., 20250-1571, or via email at dennis.rankin@wdc.usda.gov    (202) 720-1953

Prior Posts:

What’s the story on the Q-1D South rebuild?

Dairyland’s N LaX-LaX 161 kV Tap maps

Plan for Q-1D South near LaX?

UPDATE: Dairyland’s Q-1 “upgrades” through La Crosse

We still don’t know what the plans are.  I’ve made several requests, nada…  Is this any way to run a transmission project?

Kimberly St

 

zero comments so far »

Please leave a comment below!

Copy link for RSS feed for comments on this post or for TrackBack URI

Leave a comment

(required)

(required)




image: detail of installation by Bronwyn Lace