Oronoco Twp Appeals Transmission Decision

NO Grid North Partners - transmission f/k/a CapX 2020 Posted on July 11, 2013 by adminJuly 11, 2013

Oronoco has Petitioned the Supreme Court to review the Appellate Court’s affirmation of the decision of the Public Utilities Commission to route CapX 2020 transmission through Oronoco Township.  I don’t have a copy of the Petition yet, they send mail … Continue reading →

Posted in Appeal, Hampton-Alma-LaCrosse | Tagged CapX 2020, Kay Nord Hunt, Oronoco Township, powerline, Public Utilities Commission, transmission line, White Bridge Road | Leave a reply

La Crosse Construction Update

NO Grid North Partners - transmission f/k/a CapX 2020 Posted on July 11, 2013 by adminJuly 11, 2013

George Nygaard sent these photos of the Briggs Road substation near La Crosse … at the count of three, let’s all get depressed… One… Two… Three…

Continue reading →
Posted in Hampton-Alma-LaCrosse | Tagged Briggs Road substation, CapX 2020, Hampton - La Crosse, powerline, transmission line | Leave a reply

Hampton substation going up!

NO Grid North Partners - transmission f/k/a CapX 2020 Posted on July 9, 2013 by adminJuly 9, 2013

I’ve been keeping an eye on the Hampton substation location, flags went up, trucks parked, and the other day when I went up to St. Paul, dirt was being moved around.  You can see it on Hwy. 52, north of … Continue reading →

Posted in Brookings Routing Docket, Hampton-Alma-LaCrosse | Tagged Brookings-Hampton, CapX 2020, CapX2020, Hampton Substation, Hampton-LaCrosse, powerline, transmission line, Xcel Energy | 2 Replies

CapX 2020 in the news!

NO Grid North Partners - transmission f/k/a CapX 2020 Posted on May 15, 2013 by adminMay 15, 2013

Yeah, I know… haven’t posted anything for a while.  But things are a happenin’ !!! From the Echo Press in Alexandria, a Letter to the Editor: Letter – Energy company’s actions are downright petty To the editor: As a retired … Continue reading →

Posted in Fargo-St Cloud, News coverage | Tagged Buy the Farm, CapX 2020, Minn. Stat. 216E.12, No CapX 2020, powerline, Subd. 4, transmission, transmission line | Leave a reply

Some History of Transmission in the Midwest

NO Grid North Partners - transmission f/k/a CapX 2020 Posted on April 30, 2013 by adminApril 30, 2013

Now, to be clear, this doesn’t go back all that far.  But I’ve been doing some research, omphaloskepsis perhaps, digging back aways into transmission, looking at where we are given the status of CapX 2020 transmission these days, and I’ve … Continue reading →

Posted in Laws & Rules, Nuts & Bolts | Tagged CapX 2020, coal, Fresh Energy, Izaak Walton League, MCEA, Minnesota Center for Environmental Advocacy, Minnesota Dept. of Commerce, NAWO, North American Water Office, Public Utilities Commission, Xcel Energy | 1 Reply

Complaint filed at FERC

NO Grid North Partners - transmission f/k/a CapX 2020 Posted on March 2, 2013 by adminMarch 2, 2013

Yesterday, Citizens Energy Task Force and Save Our Unique Lands filed a Complaint at the Federal Energy Regulatory Commission that the Midwest Reliability Organization (MRO), Midwest Independent Transmission System Operator (MISO) and the CapX 2020 Applicant utilities had violated NERC … Continue reading →

Posted in FERC | Tagged CapX 2020, Citizens Energy Task Force, Federal Energy Regulatory Commission, FERC, instability, power line, Save Our Unique Lands, transmission line | Leave a reply

Why a STrib puff piece for CapX 2020?

NO Grid North Partners - transmission f/k/a CapX 2020 Posted on February 24, 2013 by adminFebruary 24, 2013

“Rodney Dangerfield is the patron saint of transmission systems,” quipped Will Kaul, vice president of transmission at Great River Energy and chairman of the CapX2020 group of 11 Minnesota utilities involved in the 800-mile project. Why would there be a … Continue reading →

Posted in News coverage | Tagged CapX 2020, environmental toadies, GRE, Great Plains Institute, HF 338, HF 438, HF 439, HF 665, S 455, SF 183, SF 4664, SF 674, transmission build-out, Wind on the Wires, Xcel Energy | 2 Replies

SD Coal Connection Announced

NO Grid North Partners - transmission f/k/a CapX 2020 Posted on February 24, 2013 by adminFebruary 24, 2013

= . Finally, the South Dakota to Minnesota transmission line is announced. Transmission equals coal, the “benefits” of transmission are realized when coal displaces natural gas, when coal can be shipped anywhere: ICF – MISO Benefits Analysis Study And that … Continue reading →

Posted in News coverage, South Dakota, Upcoming Events | Tagged CapX 2020, No CapX 2020, powerline, South Dakota, transmission for coal, transmission line | 1 Reply

Schedule for Minnesota appeals

NO Grid North Partners - transmission f/k/a CapX 2020 Posted on October 15, 2012 by adminOctober 15, 2012

The Minnesota appeal of the Hampton-Rochester-La Crosse CapX 2020 transmission line is lumbering forward.  Today we reached an agreement for briefing and also that no transcripts would be required because they are already a part of the record (and those … Continue reading →

Posted in Appeal | Tagged CapX 2020, Minnesota Court of Appeals, No CapX 2020, Oronoco Township, powerline, St. Paul's Lutheran School and Church, transmission line | 1 Reply

CapX Compliance Filing – what’s goin’ on?

NO Grid North Partners - transmission f/k/a CapX 2020 Posted on October 10, 2012 by adminOctober 10, 2012

Yesterday a filing came over the wire, and I finally got around to reading it.  Odd.  It’s a Compliance Filing, which means that Xcel is filing it to show that they’re in compliance with the CapX 2020 order, in this … Continue reading →

Posted in Uncategorized | Tagged CapX 2020, Citizens Energy Task Force, No CapX 2020, Northern States Power, United Citizens Action Network, Xcel Energy | Leave a reply

Post navigation

← Older posts
Newer posts →
pages
  • About
  • Maps – CapX 2020
search
categories
  • * CURRENT PROJECTS
    • Big Stone-Alex-Big Oaks
    • Brookings-Lyon Co & Helena-Hampton
    • HVDC Modernization Project
    • Lyon Co. – Sherco – MN Energy CON
    • Northland Reliability Project
    • Prairie Island Dry Cask Storage
    • Wilmarth-North Roch-Tremval WI
    • Xcel Energy IRP
  • * OLDER TRANSMISSION
    • Appeal
    • BadgerCoulee – Wisconsin
    • Bemidji-Grand Rapids
    • Brookings Routing Docket
    • Cardinal-Hickory Creek
      • RUS EIS
    • Fargo-St Cloud
    • Hampton-Alma-LaCrosse
    • ITC MN & IA 345 kV
    • Q-1 Upgrade
    • South Dakota
    • St.Cloud-Monticello
  • Buy the Farm
  • Cost Recovery
  • FERC
  • Laws & Rules
  • News coverage
  • Nuts & Bolts
  • PUC Docket
    • Information Requests
  • Rate Case – Transmission
  • Reports – Documents
  • Uncategorized
  • Upcoming Events
  • Wisconsin
archives
  • 2024
  • 2023
  • 2022
  • 2021
  • 2019
  • 2018
  • 2017
  • 2016
  • 2015
  • 2014
  • 2013
  • 2012
  • 2011
  • 2010
  • 2009
  • 2008
  • 2007
©2025 - NO Grid North Partners - transmission f/k/a CapX 2020
↑