NO Grid North Partners - transmission f/k/a CapX 2020 Posted on January 6, 2011 by adminJanuary 6, 2011

Today NoCapX 2020 and United Citizens Action Network filed Exceptions to ALJ Richard Luis’ Recommendation/Non-Recommendation filed on December 22, 2010. Exceptions to Recommendation – Brookings Remand

Continue reading →
Posted in Brookings Routing Docket | Tagged ALJ Richard Luis, Belle Plaine Crossing, Brookings to Hampton, Exceptions, LeSueur Crossing, MnDOT, MOES, Office of Energy Security | Leave a reply

Fargo-St. Cloud DEIS is out!

NO Grid North Partners - transmission f/k/a CapX 2020 Posted on September 8, 2010 by adminSeptember 8, 2010

DEIS IS OUT AND DEIS COMMENT MEETINGS ARE SCHEDULED MOES has released the Draft Environmental Impact Statement for the CapX 2020 Fargo-St. Cloud line (09-1056): Notice of DEIS Release and Public Meetings Fargo-St. Cloud DEIS page – VIEW AND DOWNLOAD … Continue reading →

Posted in Fargo-St Cloud | Tagged CapX 2020, Draft Environmental Impact Statement, GRE, Minnesota Dept. of Commerce, MOES, Office of Energy Security, Otter Tail Power, Xcel Energy | Leave a reply

Report on Prehearing Conference for Alma/LaX line

NO Grid North Partners - transmission f/k/a CapX 2020 Posted on August 11, 2010 by adminAugust 11, 2010

Monday was the Prehearing Conference for the CapX 2020 Hampton-LaCrosse/Alma transmission line. NoCapX 2020 and U-CAN are the only parties thus far – CETF was missed! The Prehearing Conference was to discuss the schedule.   We had some observers, one from … Continue reading →

Posted in Hampton-Alma-LaCrosse | Tagged CapX 2020 Hampton-Alma, CapX 2020 Hampton-LaCrosse, MOES, OAH, Office of Administrative Hearings, Office of Energy Security, Prehearing conference | Leave a reply

Notes from Friday

NO Grid North Partners - transmission f/k/a CapX 2020 Posted on December 19, 2009 by adminDecember 19, 2009

Conductor on loan from New England Judge Luis has taken my subpoena request under advisement — I’m wanting to have Fish & Wildlife come in and explain their position on the impacts of CapX crossings over the Minnesota River.  Now … Continue reading →

Posted in Brookings Routing Docket | Tagged Brookings, CapX 2020, electromagnetic fields, EMF, lying sacks of shit, magnetic fields, Minnesota Dept. of Commerce, Office of Energy Security, powerline, transmission, transmission line, US Fish & Wildlife Service, USFWS | Leave a reply
pages
  • About
  • Maps – CapX 2020
search
categories
  • * CURRENT PROJECTS
    • Big Stone-Alex-Big Oaks
    • Brookings-Lyon Co & Helena-Hampton
    • HVDC Modernization Project
    • Lyon Co. – Sherco – MN Energy CON
    • Northland Reliability Project
    • Prairie Island Dry Cask Storage
    • Wilmarth-North Roch-Tremval WI
    • Xcel Energy IRP
  • * OLDER TRANSMISSION
    • Appeal
    • BadgerCoulee – Wisconsin
    • Bemidji-Grand Rapids
    • Brookings Routing Docket
    • Cardinal-Hickory Creek
      • RUS EIS
    • Fargo-St Cloud
    • Hampton-Alma-LaCrosse
    • ITC MN & IA 345 kV
    • Q-1 Upgrade
    • South Dakota
    • St.Cloud-Monticello
  • Buy the Farm
  • Cost Recovery
  • FERC
  • Laws & Rules
  • News coverage
  • Nuts & Bolts
  • PUC Docket
    • Information Requests
  • Rate Case – Transmission
  • Reports – Documents
  • Uncategorized
  • Upcoming Events
  • Wisconsin
archives
  • 2024
  • 2023
  • 2022
  • 2021
  • 2019
  • 2018
  • 2017
  • 2016
  • 2015
  • 2014
  • 2013
  • 2012
  • 2011
  • 2010
  • 2009
  • 2008
  • 2007
©2025 - NO Grid North Partners - transmission f/k/a CapX 2020
↑